Yerevan Thermal Power Plant

From Infogalactic: the planetary knowledge core
Jump to: navigation, search
Yerevan Thermal Power Plant
New Yerevan Thermal Power Plant.jpg
Yerevan Thermal Power Plant (new unit)
Location of Yerevan Thermal Power Plant in Armenia
Official name Yerevan TPP
Country Armenia
Location Yerevan
Coordinates Lua error in package.lua at line 80: module 'strict' not found.
Status Operational
Construction began <templatestyles src="Plainlist/styles.css"/>
  • 1961 (old plant)
  • 2007 (new plant)
Commission date <templatestyles src="Plainlist/styles.css"/>
  • 1963 (old plant)
  • 22 April 2010 (new plant)
Decommission date 2010 (old plant)
Owner(s) Yerevan TPP CJSC
Thermal power station
Primary fuel natural gas
Secondary fuel fuel oil
Tertiary fuel coal
Cogeneration? yes
Combined cycle? yes
Power generation
Units operational 1 X 242 MW
Units decommissioned 5 X 50 MW
2 X 150 MW
Thermal capacity 434.9 GJ
Nameplate capacity 242 MW

Yerevan Thermal Power Plant (Armenian: Երևանի համակցված շոգեգազային ցիկլով էլեկտրակայան) is a thermal power plant located about 10 kilometres (6.2 mi) from Yerevan, Armenia.[1] An older, obsolete plant was fueled by natural gas and fuel oil, while the new combined-cycle plant is powered by natural gas and has a capacity of 242 megawatts. It produces a quarter of the country's electricity and is responsible for seasonal electricity swaps with Iran.[2] The director general of the power plant is Hovakim Hovhannisyan.[3][4]

History

Old thermal plant

The Teploelectroproject Institute began planning the Yerevan Thermal Power Plant in 1959. Construction began in 1961, and 1963 saw the commission of the first turbine, with 50 megawatts of electrical capacity. (The operating company was established at the same time.)[5] It was the first large-scale thermal power plant in Armenia.[3] After the last power turbine was commissioned in 1967, the plant consisted of seven units, with 550 megawatts of electrical power and 630 GCal/h of thermal capacity.[5] Five units had electrical capacity of 50 megawatts each, and two units had electrical capacity of 150 megawatts each.[6]

After the new plant opened in 2010, the old plant was closed. By that time, only one unit remained operational.[1] However, there is a plan to rehabilitate two 50-megawatt units of the old plant to process coal from Nagorno-Karabakh.[3][7] In 2014, equipment was installed and a small-scale test was carried out.[3]

New combined-cycle plant

A plan to privatize the power station was reconsidered in 2003.[1] Preparations for construction of the new combined cycle co-generation plant next to the existing plant started in 2005.[3] The project cost US$247 million, which was covered by a ¥26,409 billion (US$241 million) loan from the Japan Bank for International Cooperation (now the Japan International Cooperation Agency).[5] The initial loan agreement was signed on 29 March 2005, and an amendment was signed on 27 May 2008.[5][3] The loan must be repaid over 40 years at an interest rate of 0.75%. The term includes a 10-year grace period in which no money is due.[1][5]

The new plant was built by GS E&C (95%) and Mitsui (5%) under a turnkey contract.[1] Tokyo Electric Power Services Company was a consultant.[1][5] A gas turbine, a generator, and auxiliary equipment were supplied by Alstom. Fuji Heavy Industries supplied a steam turbine, Sedae Enertech Company supplied a heat recovery steam generator, and Honeywell supplied an automatic control system.[5][8][9] Construction started in December 2007 and was finished in March 2010. The new plant was inaugurated by Armenian president Serzh Sargsyan on 22 April 2010.[10]

Additional units may be built.[1][3] In 2015, it was announced that Renco S.p.a. would build and operate a $215 million, 234-megawatt unit.[11]

Characteristics

The old plant, which consisted of seven units, had 550 megawatts of electrical power and 630 GCal/h of thermal capacity. It included two К-150-130-type turbines (150 megawatts of electrical capacity each), four PT-50-130/13-type and one Р-50-130/13-type turbines (50 megawatts of electrical capacity each), two TGM-94 boilers (500 t/h of steam capacity each), and five TGM-84 boilers (420 t/h of steam capacity each).[5]

The total installed capacity of the new plant is 271.1 megawatts, of which electrical capacity is 242 megawatts and thermal capacity is 434.9 GJ/h.[7] The GT13E2 MXL gas turbine, manufactured by Alstom, has a capacity of 179.9 megawatts, and the steam turbine, manufactured by Fuji Heavy Industries, has a capacity of 63 megawatts.[5] The plant produces a quarter of the country's electricity.[4] It uses Iranian gas supplied through the Iran–Armenia gas pipeline. For each cubic meter of natural gas obtained from Iran, three kilowatt hours of electricity are provided; 38% goes to Iran, while 62% is sold domestically.[12][13] Construction of the new plant helped reduce the electricity production cost from 400 Armenian drams per kilowatt hours to 160–170 drams per kilowatt hour.[1][14]

The plant is equipped with GT13E2 MXL gas turbines.[3] It has 179.9 megawatts of capacity and operates in two modes with 36.4% efficiency. The steam turbine has 63 megawatts of electrical capacity and 103.7 GCal/h of heat capacity.[5]

The new plant has 71 employees, while the old plant had 986 employees.[3] The new plant is almost 70% more efficient than the old.[3] Compared with the Hrazdan Thermal Power Plant, it uses half as much fuel: no more than 256 grams (9.0 oz) per kilowatt hour of electricity.[3][10] Sulfuric acid emissions are tens of times lower, and nine times less nitric oxides (NOx) are emitted. Carbon dioxide (CO2) emissions were reduced by more than half, and emissions of carbon monoxide (CO) are about 38 times lower. Water consumption is more than three times lower.[5]

See also

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 Lua error in package.lua at line 80: module 'strict' not found.
  2. Lua error in package.lua at line 80: module 'strict' not found.
  3. 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 Lua error in package.lua at line 80: module 'strict' not found.
  4. 4.0 4.1 Lua error in package.lua at line 80: module 'strict' not found.
  5. 5.00 5.01 5.02 5.03 5.04 5.05 5.06 5.07 5.08 5.09 5.10 Lua error in package.lua at line 80: module 'strict' not found.
  6. Lua error in package.lua at line 80: module 'strict' not found.
  7. 7.0 7.1 Lua error in package.lua at line 80: module 'strict' not found.
  8. Lua error in package.lua at line 80: module 'strict' not found.
  9. Lua error in package.lua at line 80: module 'strict' not found.
  10. 10.0 10.1 Lua error in package.lua at line 80: module 'strict' not found.
  11. Lua error in package.lua at line 80: module 'strict' not found.
  12. Lua error in package.lua at line 80: module 'strict' not found.
  13. Lua error in package.lua at line 80: module 'strict' not found.
  14. Lua error in package.lua at line 80: module 'strict' not found.