Anholt Offshore Wind Farm
Anholt Offshore Wind Farm | |
---|---|
Location of Anholt Offshore Wind Farm in Denmark
|
|
Country | Denmark |
Location | Kattegat near Norddjurs |
Coordinates | Lua error in package.lua at line 80: module 'strict' not found.[1] |
Status | Operational |
Construction began | 2012 |
Commission date | 4 September 2013 |
Construction cost | 10 billion Danish kroner |
Owner(s) | DONG Energy |
Wind farm | |
Max. water depth | 14–17 m (46–56 ft) |
Distance from shore | 21 km (13 mi) |
Power generation | |
Units operational | 111 |
Make and model | Siemens Wind Power: SWT-3.6-120[2] |
Nameplate capacity | 400 MW |
Capacity factor | 48.7 %[3] |
Anholt Offshore Wind Farm is a Danish offshore wind power wind farm in the Kattegat, between Djursland and Anholt island. With a nameplate capacity of 400 megawatts (MW), it is the third largest offshore wind farm in the world (along with BARD Offshore 1) and the largest in Denmark. A cable from the wind farm to Anholt replaces most of the diesel-powered electricity on the island.[4]
Contents
Project
Economy
The project was conceived in February 2008, as part of the Danish government's Energy Policy Agreement.[5] The wind farm costs an estimated 10 billion Danish kroner (€1.35 bn, US$1.65 bn). During operation, DONG receives a feed-in tariff of 1.051 DKK/kW·h (17 US¢/kW·h) for the first 20 TW·h (about 12–13 years of production),[6] whereas the 207 MW Rødsand 2 receives 0.629 DKK/kW·h for 10 TW·h.[7]
DONG Energy was the only bidder for the project, and received the license to build it in 2010.[8][9] Newsmedia and politicians suggest a tight schedule with tough sanctions as reasons for the single bid and higher price,[10][11] and the subsequent Horns Rev 3 offshore wind farm had 4 bidders in 2015 and costs 0.77 DKK/kW·h, well below the 105 øre at Anholt.[12]
Technology
DONG contracted Siemens Wind Power to supply 111 3.6 MW wind turbines for the project,[13] placed in 14 metres (46 ft) water depth.[1]
The transformer platform increases voltage from 33 to 220 kV for transporting the alternating current power 25 kilometres (16 mi) to land through a single 3-conductor cable (diameter 26 cm or 10 in)[14] and a further 56 km (35 mi)[15] to Trige (near Aarhus) where a 400 kV main power hub can distribute the power.[16][17]
The agreement requires first power to be produced before the end of 2012, and be fully commissioned before the end of 2013.[1] In March 2011, DONG Energy sold 50% of the Anholt wind farm to a consortium consisting of PensionDanmark (30%) and PKA (Pensionskassernes Administration, 20%) for DKK 6 billion (US$1.14 billion) payable in 4 rates between 2011 and 2013.[18][19]
Usually, turbines are placed in a grid pattern of lines and rows. But the turbines of AOWF are placed in an unusual pattern, governed by two principles: put most of them along the edges, and put most in undisturbed airflow from the main direction, which is West-southwest. This would increase production by 1.5%, a lifetime value of more than 100m DKK.[20]
Construction
On 31 December 2011, the heavy lift vessel (HLV) Svanen placed the first foundation monopile.[21]
Official construction of the wind farm started on 13 January 2012.[22]
The first turbine was installed on 3 September and connected to the Danish power grid on 21 September.[23]
In May 2013, AOWF became Denmark's largest wind farm when 59 turbines were grid connected, totalling 212MW and surpassing Horns Rev 2. The vessel Sea Installer managed to erect a complete tower (saving time), and installed a wind turbine in 7 hours.[24]
On 19 May 2013, the installation vessel Sea Power erected the last of the 111 turbines at Anholt Offshore Wind Farm.[25]
The wind farm achieved full power in June 2013,[26][27] and was inaugurated and commissioned on 4 September 2013.[10][28]
Operation
The connection cable has been out of service two times; first the land cable failed for a week in 2014 costing Energinet.dk 9 million DKK in compensation to DONG. In February 2015 the sea cable failed, and Anholt island reverted to its diesel engines.[29]
As of 2015[update], the farm has produced 4,427 GWh.[3]
See also
Wikimedia Commons has media related to Anholt Offshore Wind Farm. |
External links
External media | |
---|---|
Images | |
Location and grid connection | |
Video | |
Plug-in wind – from offshore wind turbine to consumer | |
Help for wind turbines | |
Race against time | |
Halfway through | |
Erecting monopile and turbine |
References
- ↑ 1.0 1.1 1.2 Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Siemens - Offshore wind power projects
- ↑ 3.0 3.1 Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Anholt offshore wind farm (in Danish) Danish Energy Agency. Accessed: 27 November 2010.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Hanne, Windemuller. Anholt Offshore Wind Farm will be the largest in Denmark Danish Energy Agency, 2 July 2010. Accessed: 27 November 2010.
- ↑ Pia C. Jensen & Steen Hartvig Jacobsen. "Wind turbines in Denmark", page 26. Danish Energy Agency, November 2009. Accessed: 4 September 2013.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ 10.0 10.1 Jan Bjerre Lauridsen & Søren Andersen. "Queen says Good Wind to giant turbines" (in Danish) Berlingske, 4 September 2013. Accessed: 4 September 2013.
- ↑ Erik Holm & Sanne Wittrup. "We should learn from Anholt" (in Danish) Ingeniøren, 8 April 2010. Accessed: 4 September 2013.
- ↑ Wittrup, Sanne. "Svenske Vattenfall skal bygge Danmarks næste havmøllepark " Ingeniøren, 26 February 2015. Accessed: 26 February 2015.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Kvarts, Thomas. About the seacable (in Danish) Energinet.dk. Accessed: 27 November 2010.
- ↑ Kvarts, Thomas. About the landcable (in Danish) Energinet.dk. Accessed: 27 November 2010.
- ↑ Damgaard, Poul. About the transformator platform (in Danish) Energinet.dk, 20 August 2010. Retrieved: 24 October 2010.
- ↑ Gaardestrup, Rikke Bille. Connection of offshore wind farm Anholt Energinet.dk, 30 November 2009. Retrieved: 24 October 2010.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Pedersen, Lars Dalsgård. DONG sells half of Anholt wind farm Energy Supply, 28 March 2011. Accessed: 10 December 2011.
- ↑ Sanne Wittrup. "Bonus for new pattern of turbines" (in Danish) Ingeniøren, 2 May 2011. Accessed: 4 September 2013.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Newsletter-May2013
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Anholf Offshore wind farm in 4C Offshore Retrieved 27 August 2013
- ↑ "VIPs cut ribbon at 400MW Anholt" Recharge News, 4 September 2013. Accessed: 4 September 2013.
- ↑ Wittrup, Sanne. "Fejl på søkabel stopper Anholt Havmøllepark i tre uger " Ingeniøren, 23 February 2015. Accessed: 23 February 2015.
- Use dmy dates from September 2013
- Articles containing potentially dated statements from 2015
- Commons category link is defined as the pagename
- Official website not in Wikidata
- Offshore wind farms in the Baltic Sea
- Wind farms in Denmark
- Buildings and structures in Central Denmark Region
- DONG Energy wind farms
- Energy infrastructure completed in 2013