E. L. Patton Yukon River Bridge

From Infogalactic: the planetary knowledge core
Jump to: navigation, search
E. L. Patton Yukon River Bridge
A beige bridge on supports spanning a brown colored river and evergreen hills in the background.
Span from the northwest
Coordinates Lua error in package.lua at line 80: module 'strict' not found.
Carries AK-11[1]
Alaska Pipeline[2]
Crosses Yukon River
Locale Yukon-Koyukuk Census Area, Alaska
Official name E. L. Patton Bridge
Other name(s) Yukon River Bridge
Patton Bridge
Owner DOT&PF
Maintained by DOT&PF
Characteristics
Total length 2,295 feet (700 m)[3]
Width 30 feet (9.1 m)[3]
History
Constructed by Manson-Osberg-Ghemm[4]
Construction begin May 1974[5]
Opened October 10, 1975[5]

The Yukon River Bridge, officially known as the E. L. Patton Bridge, is a girder bridge spanning the Yukon River in Yukon-Koyukuk Census Area, Alaska, United States. The bridge carries both the Dalton Highway and the Alaska Pipeline in connecting Fairbanks with Deadhorse near the Arctic Ocean and the Prudhoe Bay Oil Field. It is the only bridge crossing of the Yukon in Alaska.[6][7]

History

As part of construction of the Trans-Alaska Pipeline System, a permanent crossing of the Yukon River became necessary in order to complete the project. In December 1973, the state announced that it would begin accepting bids for the construction of the span.[2] To be constructed as joint venture between the Alyeska Pipeline Service Company and the State of Alaska, the bridge was to be supported by tiers anchored to bedrock beneath the river. At its highest point, the span would rise approximately 200 feet (61 m) above the river with its length changing by nearly 2 feet (0.61 m) between the summer and winter months.[2] A consortium called Manson-Osberg-Ghemm was selected to construct the bridge with a bid of $31 million to be complete by December 1975.[4]

With construction commencing in May 1974,[5] in the following August the project suffered its only major construction delay with the failure of a cofferdam.[4] The cofferdam failed at its base where workers were working to set one of the concrete and steel bridge piers. The dams themselves had dimensions of 54 feet (16 m) wide by 38 feet (12 m) long with a depth of 37 feet (11 m).[4]

Although still not yet complete at the time, the bridge celebrated its ceremonial ribbon-cutting on October 10, 1975.[5] This allowed Alyeska to start utilize the span, thus eliminating the need to construct an ice bridge that winter to transport materials across the river.[5] The bridge would remain under the control of Alyeska until the completion of the Alaska Pipeline, at which control of both the bridge and haul road was turned over to the state. The state issued its final use permit on October 30, 1975.[8]

After both debate and litigation as to who would be allowed to use the haul road and bridge crossing, in October 1978 both were turned over to the state.[9] In March 1982, the state officially named the bridge in honor of Edward Patton, former president of the Alyeska Pipeline Service Company during construction of the pipeline.[10]

Description

The bridge has a length of 2,295 feet (700 m) and a width of 30 feet (9.1 m).[3] The driving surface of the span is of timber construction supported by a steel deck attached to a pair of steel box girders.[1] The wooden deck has been replaced in 1981, 1992, 1999 and 2007.[1]

References

  1. 1.0 1.1 1.2 Lua error in package.lua at line 80: module 'strict' not found.
  2. 2.0 2.1 2.2 Lua error in package.lua at line 80: module 'strict' not found.
  3. 3.0 3.1 3.2 Lua error in package.lua at line 80: module 'strict' not found.
  4. 4.0 4.1 4.2 4.3 Lua error in package.lua at line 80: module 'strict' not found.
  5. 5.0 5.1 5.2 5.3 5.4 Lua error in package.lua at line 80: module 'strict' not found.
  6. Lua error in package.lua at line 80: module 'strict' not found.
  7. Lua error in package.lua at line 80: module 'strict' not found.
  8. Lua error in package.lua at line 80: module 'strict' not found.
  9. Lua error in package.lua at line 80: module 'strict' not found.
  10. Lua error in package.lua at line 80: module 'strict' not found.