Taum Sauk Hydroelectric Power Station

From Infogalactic: the planetary knowledge core
Jump to: navigation, search
Water stored in the upper reservoir is used to generate electricity during peak demand
File:Taum Sauk power plant.jpg
The two generators can each produce up to 225 MW of power
File:Taum Sauk upper reservoir full 2005.jpg
The original upper reservoir, full to within a few feet of the top of the parapet wall

The Taum Sauk pumped storage plant is in the St. Francois mountain region of the Missouri Ozarks about 90 miles (140 km) south of St. Louis near Lesterville, Missouri, in Reynolds County. It is operated by the AmerenUE electric company.

The pumped-storage hydroelectric plant was built to help meet peak power demands during the day. Electrical generators are turned by water flowing from a reservoir on top of Proffit Mountain into a lower reservoir on the East Fork of the Black River. At night, excess electricity on the power grid is used to pump water back to the mountaintop.

The Taum Sauk plant is a pure pump-back operation: unlike most other pumped storage sites, there is no natural primary flow available for generation. It is therefore a net consumer of electricity; the laws of thermodynamics dictate that more power is used to pump the water up the mountain than is generated when it comes down. However, the plant is still economical to operate because the upper reservoir is refilled at night, when the electrical generation system is running at low-cost baseline capacity. This ability to store energy led its operator to call Taum Sauk "the biggest battery that we have."[1]

The Taum Sauk plant was among the largest of its kind when construction began in 1960. It went into operation in 1963 with two reversible pump-turbine units that could each generate 175 megawatts (235,000 hp) of power. In 1999, the plant was upgraded with units capable of 225 megawatts (302,000 hp) apiece.

On December 14, 2005, a catastrophic failure in the upper reservoir dam put the plant out of operation until it was rebuilt, recertified, and reopened on April 21, 2010.[2] The new upper reservoir dam, rebuilt from the ground up, is the largest roller-compacted concrete dam in North America.[3]

The plant was named an IEEE Milestone in October 2005, just months before the Upper Reservoir failed.[4]

Size and location

The upper reservoir can hold about 1.5 billion gallons of water (5.7 million m3; 4,600 acre feet (5,700,000 m3) behind a wall nearly 100 feet (30 m) tall.[5] It sits 800 feet (240 m) above the 440 megawatts (590,000 hp) hydroelectric plant, which gives it a greater head than that of Hoover Dam. The two are connected by a 7,000-foot (2,100 m) tunnel bored through the mountain.

The Taum Sauk upper reservoir sits atop Proffit Mountain, not Taum Sauk Mountain about 5 miles (8.0 km) to the east. It is visible from Route 21 north of Centerville and from Route N approaching Johnson's Shut-ins State Park from the south.

Before the failure of the upper reservoir, visitors could drive to the top of Proffit Mountain and walk to an observation deck above the reservoir. Ameren operated a museum at the entrance gate highlighting the geologic and natural history of Missouri. The power plant was frequently visited by geology students because of a striking example of Precambrian/Cambrian unconformity in the rock layers exposed by the plant's construction.

Leaks and lining

There had been minor leaks in the reservoir since it was constructed. A pumpback station was eventually installed to collect and return leakage to the reservoir. From September 13, 2004, to November 15, 2004, Geo-Synthetics installed lining material to reduce leaks.[6]

Upper reservoir failure

A large section of the upper reservoir failed, draining over a billion gallons of water in less than half an hour.
File:Taum Sauk reservoir-FERC 12 22 05 02.jpg
A broad swath of dense forest was washed away and scoured to bedrock by the escaping flow. Source: FERC
File:Tscompare.jpg
Aerial photos showing upper reservoir before and after failure

At 5:12 a.m. on December 14, 2005, the northwest side of the upper reservoir was overtopped when water continued to be pumped from the lower reservoir after the upper was full. This led to the catastrophic failure of a triangular section of the reservoir wall and the release of a 1,000 million US gallons (3.8 Gl) of water in twelve minutes. The sudden release sent a 20-foot (6.1 m) crest of water down the Black River.

A combination of design and construction flaws, continuing to operate the dam when the primary system for gauging the water level was known to be inaccurate (gauge pipes had become detached), moving the "failsafe" secondary gauging system above the actual height of the dam to avoid false positives, and operating the dam in an unsafe manner by allowing the water against the parapet which was intended only as a splash guard caused the upper reservoir dam to overtop.[7][8] There was no overflow spillway in the original reservoir.

A memo from Richard Cooper, superintendent of Ameren's Taum Sauk Hydroelectric Plant, indicated that the reservoir had a "Niagara Falls" style overflow on September 27 at the same spot that was breached (caused by wave action related to winds from Hurricane Rita.) Another Cooper memo had also indicated that Cooper had warned that gauges used to monitor the water height in the reservoir were malfunctioning in October.

No one was killed by the failure. The superintendent of Johnson's Shut-Ins and Taum Sauk State Parks, Jerry Toops, his wife and three children were swept away when the wall of water obliterated their home. They survived, suffering from injuries and exposure. The children were transported to a hospital in St. Louis and later released. One child was treated for severe burns which resulted from heat packs applied by rescue workers as treatment for hypothermia.

The dam of the lower reservoir, which by design is able to hold much of the capacity of the upper reservoir, withstood the onslaught of the flood. By storing most of the deluge it spared towns downstream, including Lesterville and Centerville, from a damaging flood. A voluntary evacuation order was issued for those areas, but there was no damage. The high water was stopped at Clearwater Lake, the dam of which was not damaged by the rising waters.[9]

Litigation and investigations

The Federal Energy Regulatory Commission fined Ameren $15 million pursuant to a settlement for the breach at Taum Sauk. This is the second highest[citation needed] fine ever levied by FERC, only outstripped by the fine and subsequent settlement against FPL regarding the 2008 Florida electricity blackout.

The State of Missouri sued Ameren for Actual and Punitive Damages alleging Ameren was reckless in its operation of the plant.[10][11]

The Missouri Highway Patrol delivered a report of its criminal investigation to the Attorney General in June 2007 which "did not name any suspect" and the Attorney General made a statement that there would be no criminal charges. According to press reports, the report states that Ameren failed to provide the identity of the person who raised the gauges meant to prevent overtopping and also states that the gauges were moved before investigators were on the scene.[12][13]

KMOX radio in St. Louis reports that the EPA assisted by the U.S. Attorney's Office has begun an investigation into violations of the Clean Water Act and has requested the Highway Patrol's report.[14]

The Public Service Commission reopened its investigation (based on the Highway Patrol report) and subsequently found the accident to be a failure of Ameren management, stating:

...the Commission can only conclude that the loss of the Taum Sauk plant was due to imprudence on the part of UE (Ameren's AmerenUE Subsidiary). UE was well-aware of the catastrophic results likely to occur if the UR (Upper Reservoir) was overtopped by over-pumping. UE knew, or should have known, that storing water against the parapet wall of a rockfill dam was “unprecedented.” UE knew,or should have known, that operating with a freeboard of only one or two feet left no margin for error and required particularly accurate control of the UR water level. Given that circumstance, UE’s decision to continue operating Taum Sauk after the discovery of the failure of the gauge piping anchoring system and the consequent unreliability of the piezometers upon which the UR control system was based is frankly beyond imprudent – it is reckless. UE also knew or should have known that the upper Warrick probes had been reset above the lowest point at the top of the UR." (PSC Report page 71, definitions of Acronyms added)

Ameren had 90 days from the date of the report to answer back to the PSC how it will meet the recommendations of the report, which include a whistle blower rule, changes in safety management structure, financial accounting for the rebuild of the upper reservoir, and single point of management for the rebuild.[15][16]

Reconstruction

File:TaumSaukReservoir underconstruction.jpg
Aerial photo of new reconstruction in late November, 2009
File:Taum Sauk Reservoir from scour-089.jpg
The completed replacement reservoir viewed from the scour created by the collapse of the original

Federal regulators approved Ameren's plan to rebuild the reservoir, and construction began in late 2007. The rebuilt structure is made entirely of roller-compacted concrete, unlike the earth-fill original. In addition to fill-detection instrumentation it incorporates a spillway to handle any overflow and a video system to monitor the water level. The USD $450.0 million cost of rebuilding the reservoir was covered mostly by insurance. The utility is prohibited from billing customers to recoup any of the cost.[citation needed]

Water was pumped into the rebuilt reservoir for the first time on February 27, 2010, and engineers monitored the response of the new structure as the water level was repeatedly raised and lowered. The final approval required from the FERC for “return to normal project operations” was received on April 1, 2010. The utility met the Missouri Public Service Commission’s in-service criteria for operations on April 15, and electricity was first generated from the new structure on April 21, 2010.[2] The new dam was recognized by the U.S. Society on Dams with its "Award of Excellence in the Constructed Project".[3]

See also

Notes

  1. Lua error in package.lua at line 80: module 'strict' not found.
  2. 2.0 2.1 Lua error in package.lua at line 80: module 'strict' not found.
  3. 3.0 3.1 Lua error in package.lua at line 80: module 'strict' not found.
  4. Lua error in package.lua at line 80: module 'strict' not found.
  5. Lua error in package.lua at line 80: module 'strict' not found.
  6. AmerenUE Taum Sauk Reservoir Lining Project at the Wayback Machine
  7. http://www.bpa.gov/power/PG/NW-HydroOperators-Forum/Materials/CaseStudyT-Sauk_Ehasz-Paul.pdf Missouri University of Science & Technology: The 2005 Upper Taum Sauk Dam Failure:A Case History
  8. http://www.ferc.gov/industries/hydropower/safety/projects/taum-sauk/staff-rpt.asp Federal Energy Regulatory Commission Staff Report
  9. http://www.stltoday.com/stltoday/news/stories.nsf/missouristatenews/story/0A4A827BA5C98DB2862570D7004F9A49?OpenDocument
  10. .http://ferc.gov/industries/hydropower/safety/projects/taum-sauk.asp
  11. http://www.ago.mo.gov/newsreleases/2006/121306b.htm Missouri Attorney General Press Release with link to Petition for lawsuit against Ameren for breach
  12. http://www.stltoday.com/stltoday/news/stories.nsf/stlouiscitycounty/story/06323A30D4407520862572F4000BDE98?OpenDocument St. Louis Post Dispatch article
  13. http://www.prnewswire.com/cgi-bin/stories.pl?ACCT=104&STORY=/www/story/06-08-2007/0004604925&EDATE= Ameren Press Release
  14. http://www.kmox.com/pages/603101.php?contentType=4&contentId=628667= Report on EPA Investigation
  15. http://www.waterpowermagazine.com/story.asp?sectioncode=130&storyCode=2047683 Water Power Magazine on PSC Report
  16. http://www.psc.mo.gov/electric/report%2010-24-07.pdf Link to PSC Report Full Text

References

External links

Lua error in package.lua at line 80: module 'strict' not found.