Auckland railway electrification

From Infogalactic: the planetary knowledge core
Jump to: navigation, search
A new AM class electric multiple unit at Puhinui in 2013, introduced as part of railway electrification in Auckland.

Auckland railway electrification occurred in phases as part of investment in a new infrastructure for Auckland's urban railway network. Electrification of the network had been proposed for several decades, with work starting in the late 2000s after funds were approved from a combination of regional (Auckland Regional Council, later Auckland Council) and central government (NZ Transport Agency) budgets.

The contract for the electrification infrastructure was awarded on 14 January 2010 to an Australian and New Zealand consortium,[1] while the contract for 57 trains was awarded on 6 October 2011 to Spanish manufacturer CAF.[2] The first public electric service was on 28 April 2014 on the Onehunga Branch.[3] Since 16 May 2015, all weekend services have been operating under electric propulsion except diesel shuttle services to Pukekohe.[4]. As of July 2015, all services are electric, with the exception of Papakura to Pukekohe, which runs a diesel shuttle service. Electrification from Papakura to Pukekohe has been proposed to the council, but isn't in any immediate plans as the cost would be too high.

Specifications

File:Redoing Railroad Triangle, Newmarket.jpg
Rail works preceding electrification, such as the triangle north of Newmarket, incorporated provision for electrification, such as base foundations. Bridge works increased clearances for the catenary.
File:06-newmarket4.jpg
The same junction as above in December 2010, with some of the traction poles in place, although not yet unfinished.

Power supply

KiwiRail is electrifying all lines between Swanson in the west and Papakura in the south at 25 kV AC,[5] the same voltage as the North Island Main Trunk between Te Rapa and Palmerston North. In contrast, the Wellington suburban network (electrified 1938–55) uses 1500 V DC.

About 3,500 masts will be installed.[6] The Onehunga Branch was the first line to be commissioned.[7]

The system is supplied by two connections to Transpower's 220 kV national grid, one at Mighty River Power's Southdown Power Station and the other at Transpower's Penrose substation. Both connections are duplicated (Penrose has limited duplication due to having only one 220/25 kV transformer), and one connection can supply the entire network if the other one fails, creating a high level of redundancy. KiwiRail says it will use less than 1% of Auckland's electricity capacity.[1] KiwiRail has also approached local lines company Vector about a possible third connection in the central city.[8]

Rolling stock

<templatestyles src="Module:Hatnote/styles.css"></templatestyles>

The decision to electrify was partly prompted by the ageing diesel train fleet becoming unreliable.[9] The fleet comprises diesel multiple units (DMUs) bought second-hand from Perth, Australia, and rebuilt British Rail Mark II carriages in push/pull configuration with DC and DFT locomotives; the Auckland Regional Transport Authority subsequently established that electric trains will be cheaper to run long term. Around the world, cities with high-frequency metropolitan passenger rail services use electric trains, partly because their quieter operation, faster travel between stations and greater environmental benefits.[5]

After electrification a small number of diesel trains will be retained to provide services to Pukekohe.[10] In May 2012, the possibility of extending electrification to Pukekohe was to be investigated by Auckland Transport.[11]

The EMUs are being delivered from 2013, with the last units in 2016.[7] In June 2013, it was confirmed they would be classified AM class (standing for Auckland Metro), with the motor car classified AMA, trailer car AMT, and motor/pantograph car AMP.[12]

Other infrastructure

Crossings, bridges and tunnels

There are 31 public level crossings between Swanson and Pukekohe and eight on the Onehunga branch. With electrification there is a need to safeguard crossings, since electric trains are quieter and more frequent. This includes bridges or tunnels in some cases, and the closure of small suburban street crossings in others.[13] Height restrictions of 4.25 metres or 5.0 metres will be imposed to keep vehicles clear of overhead wires.[14]

The Broadway overbridge in Newmarket and Parnell Tunnel were amongst the first of about 40 structures that needed modification before electric trains can run.[15][16] Tracks are being lowered in Purewa Tunnel on the Eastern Line.[17]

Signalling upgrades

The programme goes hand in hand with a $90 million upgrade to the signalling system.[6]

Station upgrades

Electrification works will go in tandem with construction of a new Parnell Railway Station,[18] and follow upgrades to stations, including Ellerslie (in combination with motorway works), Onehunga (lengthening for 3-car units) and Mount Albert (amenity upgrades).[7]

Maintenance depot

Funding arrangements for the rolling stock purchase included the construction of a maintenance depot and stabling facilities.[19] After looking at potential sites, 4.4 hectares of the old Winstone Quarry in Wiri (next to the South-Western Expressway and bordered by Roscommon and Wiri Station Roads) was selected, being large enough to house all the facilities required and adjacent to the NIMT railway line.[20]

Significant earthworks to prepare the site commenced in January 2011 and in May 2012 a NZ$40 million contract to construct the facility was awarded to Downer New Zealand Limited.[21] The facility was officially opened on 5 July 2013[22] and joint operational control was handed over to the train operator Transdev Auckland Limited and train supplier & maintenance operator CAF on 28 August 2013. The cost of the depot including land, construction and facility equipment was approximately NZ$100 million.

The facility includes six kilometres of sidings and a 7650 square metre depot building consisting of office facilities and the main workshop where servicing of the 57 electric trains takes place. The workshop has seven maintenance berths and has overhead gantry cranes & jacking systems for lifting the trains, high-level platforms to access train roofs, under-floor pits and a wheel lathe. There are an automatic train wash and covered platforms to facilitate cleaning of the inside of the trains.[20] The facility has been future proofed to maintain a fleet of up to 109 electric trains.[23]

The ground floor offices house CAF and the first floor Transdev and staff amenities. The Transdev offices include the depot control office and driver training facilities, which include two train simulators. Each simulator is laid out exactly like the driver’s cab with a large flat screen display in place of the windscreen that displays the view that the driver would see from the cab. The display is programmed with the Auckland railway network, filmed in 2012 and converted into video graphics. The simulator can be set to simulate daytime or night-time and includes a range of weather conditions, and it can simulate faults in the train and emergency situations.[24]

Train movements within the facility are controlled by Transdev staff from the depot control office.

The stabling capacity is 28 electric trains. There are other facilities for stabling at Henderson, Parnell and Papakura.

Funding

The Auckland Regional Council envisaged that a regional fuel tax of five cents per litre would be required to pay for the trains, the upgrade of other rolling stock, above-track infrastructure development including stations and maintenance facilities, ferry terminal upgrades and other transport infrastructure including integrated smartcard ticketing, and the council was to fund the Auckland Regional Transport Authority to buy electric trains and to operate services, and to provide stabling and maintenance facilities.[5] The infrastructure was to be paid from national funds.

However, the Fifth National Government cancelled the proposed tax, with the electrification to be paid for by central government. This move has been heavily criticised for leaving the electrification in doubt for a time, for delaying parts of the project, such as train tendering,[25] and for putting control of Auckland public transport into Wellington's hands.

In late 2009, the government confirmed that $500 million in loans would be extended to KiwiRail to enable it to proceed with tendering for the rolling stock, a process that the cancellation of the fuel tax had interrupted by at least half a year.[26] The fact that the money was only a loan, with no means provided for Auckland or KiwiRail to raise extra funds to repay it (as was intended to be done with the regional fuel tax), was criticised strongly in Auckland, as it would mean that Auckland would pay for the trains yet not own them.[27]

In mid-2011, after long negotiations between Auckland Council/Auckland Transport and the government, it was announced that the trains would be owned by Auckland, with Auckland paying approximately half of the cost from rates, and paying annual track access charges to KiwiRail and any potential purchase price increases as the winning tenderer is finalised.[19]

Timeline

2007, Electrification announced

It was announced on 17 May 2007 (as part of the 2007 New Zealand budget) that electrification would proceed, to be complete in 2013.[10]

2008, Regional fuel tax law passed

On 3 July 2008 a law was passed allowing regional fuel taxes to fund large capital projects, of up to 10c a litre but limited to 2c in 2009 and 5c in 2010. The National Party criticised the funding mechanism. [28]

2009, Regional fuel tax cancelled

Before the regional fuel tax could be implemented a change in government occurred, and the incoming National government cancelled the fuel tax in early 2009, though electrification was still to be funded.

2009, Government funding confirmed

In November 2009, government confirmed $500 million in loans to KiwiRail to allow the interrupted purchasing process for the electric trains to continue.[26] [This was later clarified as a loan that Auckland would have to repay, without a mechanism to fund the extra cost. After negotiations between central and local government, this was reduced in severity by government providing over half of the purchase cost as a subsidy, with the rest still to be paid from rates.]

2010, Electrification contract awarded

On 14 January 2010 KiwiRail announced that it has awarded the contract for electrification to a consortium of Hawkins Infrastructure, a division of New Zealand company Hawkins Construction, and Laing O'Rourke Australia, for NZ$80 million.[6]

2011, Construction of EMU maintenance and stabling depot begins

4.4 hectares of the old Winstone Quarry in Wiri was selected as the site of a maintenance and stabling facility for the new trains. Earthworks preparing the site started in January 2011 and construction of the 7650 sq m building and the six kilometres of sidings in the stabling area commenced in May 2012.[20]

2011, Train manufacture contract awarded

On 6 October 2011, CAF was confirmed as the successful tenderer, for approximately $400 million.[2]

2013, Wiri EMU maintenance and stabling depot opened

On 5 July 2013 Auckland Mayor Len Brown officially opened the facility.[22]

2013, The first electric train is delivered to the depot

On 26 August 2013 the first train (unit number AM 103) was delivered by truck to the depot for certification.[29] The train was officially unveiled during a ceremony at the depot on 12 September 2013.[30]

2014 Scheduled EMU passenger services begin

On 28 April 2014 the first EMU passenger trains entered regular service between Britomart and the Onehunga Branch line. Three EMUs were used that day with unit AM 129 being the first in service, departing Onehunga at 05:46 followed by AM 116 at 06:10 and AM 103 used as a standby spare.

July 2015, Full electric service

On 20 July 2015, electric trains began operating all services between Swanson and Papakura, seven days a week.

Stages of completion

KiwiRail announced the works would be implemented in five phases:[6]

Stage 1

Stage 2

  • Western Line, Morningside-Swanson

Stage 3

Stage 4

Stage 5

Progress

During the summer 2011-2012 shutdown, the approaches to Britomart were rebuilt to allow for electrification, masts installed and holes bored, and wiring completed in some areas.[31] During the 2013-2014 shut-down, the complex job of wiring Quay Park Junction, The Strand stabling facility and Britomart was completed.[32] By January 2014 wires had been installed:

  • Western Line: Swanson-Mount Albert, Newmarket-Britomart;
  • Southern Line: Britomart-Papakura;
  • Eastern Line: Britomart-Purewa Tunnel south end;
  • Manukau Branch (near complete);
  • Onehunga Branch.[32]

Services were planned to start during April 2014[33] and the first scheduled electric train service (from Britomart to Onehunga) took place on 28 April 2014.

The project was completed on 20 July 2015 with full electric train service across the network.[34]

Future expansion

The City Rail Link, for which enabling works are to begin in October 2015,[35] will be electrified as part of Auckland's railway electrification.

Currently services between Pukekohe and Papakura are operated by ADL/ADC class diesel multiple units. The Draft future urban land supply strategy states electrification of the network would be extended southwards to Pukekohe once the special housing area at Paerata is opened up in the "second decade" of the plan, that is by 2030.[36] A petition for the electrification to be undertaken sooner was started by a local resident of Pukekohe.[37]

See also

References

  1. 1.0 1.1 Lua error in package.lua at line 80: module 'strict' not found.
  2. 2.0 2.1 Lua error in package.lua at line 80: module 'strict' not found.
  3. Lua error in package.lua at line 80: module 'strict' not found.
  4. Lua error in package.lua at line 80: module 'strict' not found.
  5. 5.0 5.1 5.2 ARC, Rail Electrification
  6. 6.0 6.1 6.2 6.3 Lua error in package.lua at line 80: module 'strict' not found.
  7. 7.0 7.1 7.2 Lua error in package.lua at line 80: module 'strict' not found.
  8. Lua error in package.lua at line 80: module 'strict' not found.
  9. Lua error in package.lua at line 80: module 'strict' not found.
  10. 10.0 10.1 21st century public transport for Auckland - Auckland Regional Transport Authority, Thursday 17 May 2007
  11. Lua error in package.lua at line 80: module 'strict' not found.
  12. Lua error in package.lua at line 80: module 'strict' not found.
  13. Lua error in package.lua at line 80: module 'strict' not found.
  14. Lua error in package.lua at line 80: module 'strict' not found.
  15. Lua error in package.lua at line 80: module 'strict' not found.
  16. Lua error in package.lua at line 80: module 'strict' not found.
  17. Lua error in package.lua at line 80: module 'strict' not found.
  18. Lua error in package.lua at line 80: module 'strict' not found.
  19. 19.0 19.1 Lua error in package.lua at line 80: module 'strict' not found.
  20. 20.0 20.1 20.2 Lua error in package.lua at line 80: module 'strict' not found.
  21. Lua error in package.lua at line 80: module 'strict' not found.
  22. 22.0 22.1 Lua error in package.lua at line 80: module 'strict' not found.
  23. Lua error in package.lua at line 80: module 'strict' not found.
  24. Lua error in package.lua at line 80: module 'strict' not found.
  25. Lua error in package.lua at line 80: module 'strict' not found.
  26. 26.0 26.1 $500m electric train boost 'historical' for Auckland - ARC - The New Zealand Herald, Tuesday 24 November 2009
  27. Lua error in package.lua at line 80: module 'strict' not found.
  28. Nats attack new fuel tax law - The New Zealand Herald, 4 July 2008
  29. Lua error in package.lua at line 80: module 'strict' not found.
  30. Lua error in package.lua at line 80: module 'strict' not found.
  31. Lua error in package.lua at line 80: module 'strict' not found.
  32. 32.0 32.1 Lua error in package.lua at line 80: module 'strict' not found.
  33. Lua error in package.lua at line 80: module 'strict' not found.
  34. Lua error in package.lua at line 80: module 'strict' not found.
  35. Lua error in package.lua at line 80: module 'strict' not found.
  36. Lua error in package.lua at line 80: module 'strict' not found.
  37. Lua error in package.lua at line 80: module 'strict' not found.

External links

  • Campaign for Better Transport (campaign for improvements to (mainly public) transport in Auckland)
  • Lua error in package.lua at line 80: module 'strict' not found.
  • Lua error in package.lua at line 80: module 'strict' not found.
  • Lua error in package.lua at line 80: module 'strict' not found.
  • Lua error in package.lua at line 80: module 'strict' not found.
  • Lua error in package.lua at line 80: module 'strict' not found.